M/S TRISHUL CONSTRUCTION v. THE STATE OF MADHYA PRADESH
Case summary
M/S TRISHUL CONSTRUCTION v. THE STATE OF MADHYA PRADESH. High Court of Madhya Pradesh judgment dated 2020-02-04. Read the judgment and case details on...
Judgment text
THE HIGH COURT OF MADHYA PRADESH WP-13847-2017 (M/S TRISHUL CONSTRUCTION Vs THE STATE OF MADHYA PRADESH AND OTHERS) Jabalpur, Dated : 04. 02. 2020 Shri Sanjay K. Agrawal, learned counsel with Shri Siddharth Sharma, learned counsel for the petitioner. Shri Saurabh Sunder, learned Govt. Advocate for the respondent/ State. With the consent, finally heard. This is second visit of the petitioner to this Court. Previously, the department issued a show cause notice dated 18. 04. 2013 (Annexure P-3) which was followed by an order of blacklisting dated 14. 07. 2016. This order of blacklisting was the subject matter of challenge in Writ Petition No. 12641/2016 decided by Division Bench of this Court on 16. 02. 2017.
The Division Bench while setting aside blacklisting order opined that the order of blacklisting has serious consequences and, therefore, before that it was imperative on the part of the respondents to issue a specific show cause notice enabling the petitioner to understand what are the exact nature of shortcomings/allegations. In turn, the respondents issued a show cause notice dated 24. 06. 2017 (Annexure P-8) which was replied by the petitioner on 07. 07. 2017 (Annexure P-9). 2. The impugned order dated 10. 07. 2017 was again passed blacklisting the petitioner for an indefinite period. Criticising the show cause notice dated 24. 06. 2017, Shri Sanjay K. Agrawal, learned counsel for the petitioner urged that the allegations in this show cause notice are also vague and it is not made clear as to what were the shortcomings on the part of the petitioner which as per the respondents was not as per the specifications. The petitioner denied the allegations in the reply.
The impugned order is passed on the basis of a defective show cause notice which cannot sustain judicial scrutiny. Since specific reasons mentioning the shortcomings were not communicated to the petitioner in the show cause notice, the petitioner was deprived to effectively defend himself. This action runs contrary to the principles of natural justice. 3. The impugned order, as per Shri Agrawal, learned counsel for the petitioner is bad in law, on account of another reason namely the blacklisting order passed was for an indefinite period. It runs contrary to the judgment of the Supreme Court reported in [(2014) 14 SCC 731], Kulja Industries Limited Vs. Chief General Manager, Western Telecom Project Bharat Sanchar Nigam Limited and others. In support of his aforesaid arguments, Shri Agrawal has also placed reliance on the judgments of the Supreme Court reported in [2015 SCC Online MP 6833], B. C. Biyani Projects Pvt. Ltd. Vs. State of M. P.
and others, Division Bench judgments of this Court in the case of M/s Sai Construction Vs. M. P. Housing and Infrastructure Development Board and another, (W. P. No. 17907/2016) and M/s Om Construction Vs. The State of Madhya Pradesh, (W. P. No. 10337/2016). 4. Sounding a contra note, Shri Saurabh Sunder, learned Govt. Advocate supported the show cause notice as well as the impugned order of blacklisting dated 10. 7. 2017 (Annexure P-1). He raised objection of availability of alternative remedy. He submits that the petitioner can putforth his defence before the Engineer-In-Chief and the said Authority will scrutinize the defence of the petitioner. 5. Faced with this, in the rejoinder submissions, Shri Agrawal, learned counsel for the petitioner urged that when principles of natural justice are grossly violated and notice itself is defective, coupled with the fact that there are no disputed questions of fact, petitioner may not be relegated to avail the alternative remedy. 6.
No other point is pressed by the parties. 7. We have heard the parties at length and perused the record. 8. Indisputably, in the previous round, this Court interfered with the show cause notice and blacklisting order because the principles of natural justice were grossly violated. Thus, relegating the petitioner to avail alternative remedy is not a rule of thumb. Indeed, it depends on the nature of violation of principles of natural justice. The show cause notice dated 24. 06. 2017 reads as under :- “izfr] esllZ f=’kwy daLVªD’ku daiuh] bZ&7@601] v’kksd lkslk;Vh vjsjk dkyksuh] Hkksiky ¼e-iz-½ fo"k;%& ty lalk/ku laHkkx iUuk ds vUrxZr fljLokgk rkykc ;kstuk ds cka/k ,oa ugj dk fuekZ. k dk;ZA &&AAAA&& fo"k;kUrxZr ty lalk/ku laHkkx iUuk ds v/khu fljLokgk rkykc ;kstuk ds cka/k ,oa ugj dk fuekZ. k dk;Z dh fufonk ftldh vuqekfur ykxr :- 1679-84 yk[k Fkh] ;w-lh-,l-vkj-ls 1-2 izfr’kr de nj ij vkidks Lohd`r dh xbZ Fkh] ftldk vuqca/k fnukad 27-04-2013 dks fd;k x;k FkkA vuqca/kkuqlkj dk;Z iw.
kZ djus dh vof/k 18&ekg ¼o"kZdky lfgr½ Fkh] vFkkZr~ dk;Z fnukad 26-10-2014 rd iw. kZ djuk FkkA fnukd 06-07-2016 ,oa 07-07-2016 dks gqbZ o"kkZ ls mDr rkykc {kfrxzLr gqvk FkkA tks vkids }kjk fd;s x;s dk;Z dk fu/kkZfjr ekin. M ¼LisflfQds’ku½ ds vuqlkj u djus dk ifjpk;d gSA {kfrxzLr Hkkx ds lq/kkj dk;Z dks vkius vius O;; ij djus dh lgefr fyf[kr esa izLrqr dh Fkh] fdUrq ckn esa lwpuk i= nsus ds mijkar Hkh lq/kkj dk;Z ugha djk;k x;k] dk;Z viw. kZ fLFkfr esa Fkk] blfy;s dk;Z dh lqj{kk dh laiw. kZ ftEesnkjh vkidh FkhA bl laca/k esa vki viuk Li"Vhdj. k fnukad 09-07-2017 rd dk;Zikyu ;a=h] ds ek/;e ls izsf"kr djsaA Li"Vhdj. k izkIr u gksus vFkok larks"ktud u ik;s tksu dh fLFkfr esa vkidk iath;u dkyhlwph esa Mkyus dh dk;Zokgh dh tkosxhA lgi= %& 'kwU;A ¼lq/khj [kjs½ eq[; vfHk;ark]” (emphasis supplied) 9. A plain reading of this notice shows that the respondents reached to a conclusion that because of rains between 06. 07. 2016 to 07. 07.
2016, the pond in question was damaged which shows that the petitioner has not worked as per the prescribed specifications. A careful reading of this notice shows that the argument of the learned counsel for the petitioner has substance. The respondents in the show cause notice have not clarified with necessary details and with accuracy and precision as to what were those specifications which were allegedly violated by the petitioner. This is trite law that a show cause notice must contain the allegations with necessary clarity so that the other side can effectively defend itself. A vague and ambiguous show cause notice is no notice in the eyes of law. Thus, in our view, show cause notice dated 24. 06. 2017 is also ambiguous and cannot be said to be legal and justifiable one as per the principles of natural justice. The impugned order is founded upon this notice and does not contain a single reason as to why the petitioner’s defence was not trustworthy.
Apart from this, no reasons are assigned as to why drastic decision for blacklisting the petitioner for an indefinite period is taken. A common string in the judgments cited by Shri Agrawal, learned counsel is that the decision to blacklist a Contractor is a drastic decision which cannot be taken without following the principles of natural justice. As analysed above, the said principles were grossly violated in the instant case also and, therefore, we are not inclined to relegate the petitioner to avail the alternative remedy. More so, when there exists no disputed question of facts in the present case. 10. In view of the foregoing analysis the impugned order dated 10. 07. 2017 cannot sustain judicial scrutiny. The same is hereby set aside. Liberty is reserved to the respondents to issue an appropriate show cause notice and take decision thereupon in accordance with law. 11. The petition is allowed to the extent indicated above. (Sujoy Paul) (Mohd. Fahim Anwar) Judge Judge AM.
Digitally signed by ANINDYA SUNDAR MUKHOPADHYAY Date: 2020. 02. 10 13:44:05 +05'30'