NAGINCHAND BANSAL, v. STATE OF MADHYA PRADESH
Case summary
NAGINCHAND BANSAL, v. STATE OF MADHYA PRADESH. High Court of Madhya Pradesh judgment dated 2020-06-30. Read the judgment and case details on LawSphereX.
Judgment text
1 HIGH COURT OF MADHYA PRADESH Writ Petition No. 8553/2020 (Naginchand Bansal and others Vs. State of M. P. and others) PRESENT : HON. SMT. NANDITA DUBEY, J (THROUGH VIDEO CONFERENCING) Jabalpur, Dated :30. 06. 2020. Shri Naman Nagrath, learned senior counsel with Shri Jubin Prasad, learned counsel for the petitioner. Shri Vivek Sharma, learned Deputy Advocate General for the respondents/State. On account of the prevailing conditions worldwide, brought about by the COVID 19 virus, this petition has been heard and decided through video conferencing, to maintain social distancing. The necessary parties have effectively been represented by their respective counsel through video conferencing. The petitioners who are having a mining lease over the land in question are aggrieved by the action of respondent no. 6-M/s L & T Construction Co. of establishing transmission line over the same.
Learned senior counsel appearing for the petitioners has pointed out to Annexure P/3, the survey report in which the petitioners' land is not mentioned. It is submitted that without acquiring the land or without giving any compensation, the mining area of the petitioners has been intended to be used illegally. He submits that petitioners have filed a representation in this regard before the Collector-Khandwa which is filed with the petition as 2 HIGH COURT OF MADHYA PRADESH Annexure P/8. It is prayed that the same may be directed to be decided at an early date. Learned Deputy AG has submitted that the representation filed by the petitioners will be decided, as per law. Considering the aforesaid, this petition is disposed of with a direction to the Collector, Khandwa to decide the representation (Annexure P/8) filed by the petitioner, within a period of six weeks from today,as per law.
Till the aforesaid representation is decided or for a period of six weeks, whichever is earlier, the respondent no. 6/ M/s L & T Construction Company is restrained from entering into and using the land of the petitioners. However, it is made clear that this Court has not opined on the merits of the case. A typed copy of this order be forwarded by the Registry to the Office of the Advocate General and to Mr. Vivek Sharma, learned Deputy Advocate General, on their respective email addresses, for intimation to the concerned respondents and compliance. (Nandita Dubey) Judge jitin Digitally signed by JITIN KUMAR CHOURASIA Date: 2020. 06. 30 14:21:07 +05'30'