SHAILENDRA KUMAR v. CHIEF SUB ENGINEER (CONSTRUCTION)
Court: High Court of Madhya Pradesh
Judgment date:
Case summary
High Court of Madhya Pradesh judgment dated 2024-01-03. SHAILENDRA KUMAR v. CHIEF SUB ENGINEER (CONSTRUCTION). Read the judgment and case details on LawSphereX.
Judgment text
IN THE HIGH COURT OF MADHYA PRADESH AT JABALPUR BEFORE HON'BLE SHRI JUSTICE GURPAL SINGH AHLUWALIA rd ON THE 3 OF JANUARY, 2024 WRIT PETITION No. 7108 of 2017 BETWEEN:- SHAILENDRA KUMAR S/O LATE BUDHRAM, AGED ABOUT 34 YEARS, WARD NO. 6 LAALBARRA ROAD, WARASEONI TEHSIL WARASEONI, DISTRICT BALAGHAT (MADHYA PRADESH) ..... PETITIONER (NONE) AND 1. CHIEF SUB ENGINEER (CONSTRUCTION) SOUTH EAST CENTRAL RAILWAY NAGPUR DIVISION (MAHARASHTRA) (MAHARASHTRA) 2. COLLECTOR (LAND ACQUISITION) BALAGHAT DISTRICT BALAGHAT (MADHYA PRADESH) 3. UPPER COLLECTOR BALAGHAT DISTRICT BALAGHAT (MADHYA PRADESH) 4. COMMISSIONER OF LANDS RECORD BALAGHAT DISTRICT BALAGHAT (MADHYA PRADESH) ..... RESPONDENTS (BY SHRI ANSHUL TIWARI - PANEL LAWYER) This petition coming on for admission this day, th e court passed the following: ORDER On 02. 01. 2024 also none had appeared for petitioner and accordingly the case was passed over. Today, also none appears for petitioner.
Signature Not Verified Signed by: VINAY KUMAR Signing time: 03-Jan-24 6:45:19 PM This petition was filed on 09. 05. 2017 and was listed on multiple occasions but arguments were not advanced on the question of admission. Even after six years, notices have not been issued so far. As none appears for petitioner, therefore it appears that petitioner must have lost his interest in prosecuting this petition. It is accordingly dismissed for want of prosecution. (G. S. AHLUWALIA) JUDGE VB* Signature Not Verified Signed by: VINAY KUMAR Signing time: 03-Jan-24 6:45:19 PM
Source: High Court of Madhya Pradesh. Dataset: Dattam Labs. CC BY 4.0. Text extracted automatically; compare with the source PDF for layout and accuracy.