BUTULU KAMPAN v. STATE OF ODISHA. High Court of Orissa judgment dated 2024-04-09. Read the judgment and case details on LawSphereX.

Judgment text

IN THE HIGH COURT OF ORISSA AT CUTTACK W. P. (C) No. 8258 of 2024 Butulu Kampan ….. Petitioner Mr. A. K. Sahoo, Advocate Vs. State of Orissa and others ….. Opposite Parties Mr. S. Nayak, ASC CORAM: DR. JUSTICE B. R. SARANGI MR. JUSTICE G. SATAPATHY ORDER 09. 04. 2024 Order No. This matter is taken up by hybrid mode. 01. 2. Heard Mr. A. K. Sahoo, learned counsel for the Petitioner. 3. The Petitioner has filed this writ petition seeking direction to Opposite Party No. 2 to take a decision on the recommendation made under Annexure-1 series taking into consideration the provision under Section 14 of the Orissa Resettlement And Rehabilitation Policy, 2006 and sanction the required amount for disbursement in favour of the Petitioner within a stipulated time. 4. Mr. A. K. Sahoo, learned counsel for the Petitioner contended that though Opposite Party No.

3-cum-Collector & District Magistrate, Nuapada has submitted the Revised Estimate towards payment of rehabilitation assistance in favour of 17 numbers of affected persons of village Dargaon as more than 75% land loss category, under Lower Indra Irrigation Project, Khariar, Dist- Nuapada vide Annexure-1 series, the same has not been considered by Opposite Party No. 2-The Director-(R&R) & Ex-Officio-cum- Additional Secretary to Government, Department of Water Resources, Odisha, Bhubaneswar and the same is pending for consideration. 5. Mr. S. S. Pradhan, learned Additional Government Advocate raised no objection to the contention made by learned counsel for the Petitioner. 6. As agreed by learned counsel for the parties and after going through the records, this Court disposes of the Writ Petition directing the Petitioner to file a fresh representation before Opposite Party No.

2-The Director-(R&R) & Ex-Officio-cum-Additional Secretary to Government, Department of Water Resources, Odisha, Bhubaneswar within 15 days. In the event, the Petitioner files such representation within the time stipulated, Opposite Party No. 2 shall consider and pass appropriate order as early as possible within a period of two months thereafter. (DR. B. R. SARANGI) JUDGE (G. SATAPATHY) JUDGE Subhasmita Signature Not Verified Digitally Signed Signed by: SUBHASMITA DAS Designation: Sr. Stenographer Reason: Authentication Location: High Court of Orissa Date: 10-Apr-2024 18:33:59