DIBRUGARH MUNICIPAL BOARD v. RACHANA JAIN AND 3 ORS

Bench: HONOURABLE MR. JUSTICE ACHINTYA MALLA BUJOR BARUA

Case summary

DIBRUGARH MUNICIPAL BOARD v. RACHANA JAIN AND 3 ORS. Gauhati High Court judgment dated 2020-06-19. Read the judgment and case details on LawSphereX.

Judgment text

Page No. # 1/2 GAHC010016962020 THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) Case No. : I. A. (Civil) 187/2020 1:DIBRUGARH MUNICIPAL BOARD DIBRUGARH, DIST. DIBRUGARH, ASSAM, REPRESENTED BY THE ADDL. DEPUTY COMMISSIONER, DIBRUGARH, ASSAM. VERSUS 1:RACHANA JAIN AND 3 ORS W/O SRI SANDEEP KUMAR JAIN, R/O MAHABIR TEXTILE, H. S. ROAD, DIBRUGARH, DIST. DIBRUGARH, ASSAM, PIN 786001 2:THE STATE OF ASSAM REPRESENTED BY THE COMMISSIONER AND SECY. TO THE GOVT. OF ASSAM URBAN DEVELOPMENT DEPTT. DISPUR GUWAHATI-06 ASSAM. 3:THE DIRECTOR OF MUNICIPAL ADMINISTRATION ASSAM DISPUR GUWAHATI 06 4:THE DEPUTY COMMISIONER DIBRUGARH DIST. DIBRUGARH ASSAM PIN 78600 Advocate for the Petitioner : MR. P J SAIKIA Advocate for the Respondent : MR. R P SARMAH Page No. # 2/2 BEFORE HONOURABLE MR. JUSTICE ACHINTYA MALLA BUJOR BARUA ORDER Date : 19-06-2020 By the order dated 27. 05.

2020 we had taken note of that the respondent Dibrugarh Municipal Board has been violating the interim orders of this Court dated 22. 02. 2019 and 27. 05. 2019 passed in WP(C) 1223/2019. Accordingly, the respondents in the Municipal Board were required to purge the contempt that they had done in order to enable the Court to proceed further in the writ petition. An affidavit has been filed incorporating the order dated 28. 05. 2020 of the Executive Officer, Dibrugarh Municipality, Dibrugarh, which is extracted below:- “In pursuance of the Hon’ble High Court’s Order dated 22. 02. 2019 and 27. 05. 2019 passed in WP(C) No. 1223 of 2019 (Rachana Jain –vs- The State of Assam) execution of the work under the “ Up gradation by interlocking Concrete Block Pavement Block in Dibrugarh Town” be stopped with immediate effect. ” We accept the order dated 28. 05.

2020 and order that no further work/activity shall be carried out by the respondent Dibrugarh Municipal Board/Dibrugarh Municipality pursuant to the work order dated 01. 02. 2019 in any manner until further order. As we have continued with the interim order, for the present there is no requirement of passing any further order in I. A. (Civil) 187/2020, which is instituted for a modification of the interim order. I. A. stands closed. However, liberty is granted to the applicant to approach again. JUDGE Comparing Assistant