- 1 - IN THE HIGH COURT OF KARNATAKA AT BENGALURU TH DATED THIS THE 9 DAY OF OCTOBER, 2020 BEFORE THE HON’BLE MR. JUSTICE R. DEVDAS WRIT PETITION No. 31483 OF 2019 (LB-BMP) BETWEEN: Arch Bishop Bengaluru Represented by GPA Holder K. Susairaj S/o. Late Kiritapa Aged about 71 yars Residing at No. 2 Govt. Pre-University College Road Krishnarajapuram Bengaluru-560 036. ... Petitioner (By Sri Ravi. H. K, Advocate) AND: 1. The Commissioner Bruhat Bengaluru Mahanagara Palike Bengaluru 2. Assistant Executive Engineer K. R. Puram Sub-Division BBMP Bengaluru-56006 3. M/s. J. J. C. Developers & Construction Private Limited Having its registered office atNo. 28/772/A2/5 - 2 - Lalithat Nagar Nandyal, Kurnool District-518001 A. P. State represented by its Managing Director Also at J. J. C. Developers Lake Vihar-2, Apartment T. C. Palya Main Road K. R. Puram, Bengaluru-560036 4. J. A. Muniraj Managing Director and Constructions M/s. Manjunatha Developers th No.

39, 5 Cross, Narasimhaiah Layout Ramamurthynagar Bengaluru-560016 5. President Lake Vihar-2 A Apartment Owners’ Welfare Society T. C. Palya Main Road K. R. Puram, Bengaluru-56036 …. Respondents (By Sri. M. C. Nagashree, AGA for R1 and R2) This Writ Petition is filed under Articles 226 and 227 of the Constitution of India praying to direct the R-1 and 2 to take action in accordance with law against the illegal construction on the schedule property by issuing a writ of mandamus This Writ Petition coming on for Orders through video conference, this day, the Court made the following: - 3 - ORDER R. DEVDAS J. , (ORAL): The learned counsel for the petitioner has drawn the attention of this Court to a Provisional Order passed by the Assistant Executive Engineer, K. R. Puram, Sub Division, BBMP on 15. 072019 under Section 321(1) and (2) of the Karnataka Municipal Corporations Act, 1976 (‘The Act’ for brevity), detailing the deviation made by respondent Nos.

3 to 5 with respect to building put up on property bearing Sy. No. 50/11, Sonnathammanahally village, T. C. Palya, K. R. Puram Hobli, Bengaluru. The learned counsel submits that it would suffice if a direction is issued to the respondent- Authorities to take forward the Provisional Notice issued by the Assistant Executive Engineer within a stipulated time. 2. In view of the said submission, no notice is ordered to R-3 to 5, this petition stands disposed of with a direction to the second respondent - Assistant Executive Engineer, K. R. Puram, Sub Division, BBMP to pursue the - 4 - Provisional Notice issued under Section 321(1) and (2) of the Act and conclude the proceedings in accordance with law as expeditiously as possible and at any rate within a period of two months from the date of receipt of copy of this order. It is ordered accordingly. Smt. M. C. Nagashree, learned Additional Government Advocate is permitted to file vakalath within four weeks. Sd/- JUDGE RB