IN THE HIGH COURT OF MADHYA PRADESH AT JABALPUR BEFORE HON'BLE SHRI JUSTICE VIVEK JAIN CONTEMPT PETITION CIVIL No. 2265 of 2018 BETWEEN:- RAMESH KUMAR SARAWGI S/O LATE SHRI JAGAT N AR AYAN SARAWAGI, AGED ABOUT 52 YEARS, OCCUPATION: BUSINESSMAN R/O VINOBA MARG WARD O. 6 P. O. AND DISTT. UMARIA (MADHYA PRADESH) ..... PETITIONER (BY SHRI SOURABH PATHAK - ADVOCATE) AND 1. MAL SINGH BHAYADIYA COLLECTOR UMRIA DISTT. UMARIA (MADHYA PRADESH) 2. ANURAG SINGH SUB DIVISIONAL (REVENUE) UMARIYA (MADHYA PRADESH) 3. DEVI BAI W/O LATE GOPICHAND, AGED ABOUT 50 Y E A R S , OCCUPATION: HOUSEWIFE PURANA PADAV UMARIYA (MADHYA PRADESH) ..... RESPONDENTS (BY SHRI ASHOK LALWANI - ADVOCATE) ................................................................................................................................................ Reserved on :- 08. 12. 2023 Pronounced on :- 29. 01.
2024 ................................................................................................................................................ This petition coming on for admission this day, th e court passed the following: ORDER The present contempt petition has been filed alleging contempt of interim order dated 05. 04. 2011 passed in W. P. No. 5372/2011. By the said order, this Court had restrained the respondent No. 4 in the said petition from raising Signature Not Verified Signed by: RAJESH KUMAR Signing time: 1/29/2024 5:33:01 PM construction on the land in question. 2. It is the contention of the petitioner that the present respondent No. 3 (respondent No. 4 in W. P. ) has started raising construction over the land in question in the year 2011, because she has obtained certain funds under PM Awas Yojana. 3. The respondent No. 3 has filed reply to the petition and has admitted that she has raised some construction, because she was in receipt of funds under PM Awas Yojana.
She has submitted that her act of raising construction has in fact increased the value of land. In para 4 of the reply, she has stated that she was not in receipt of any intimation that the interim order dated 05. 04. 2011 had been extended or revived during the last period of seven years. 4. Upon perusal of the record of writ petition, it is seen that the interim order dated 05. 04. 2011 was operative only till the next date of hearing. It was continued on 11. 02. 2013 and 03. 04. 2013. On 20. 01. 2015, 20. 02. 2015 and 18. 03. 2015, the said interim order was not continued. On 05. 05. 2015, the writ petition was dismissed for want of prosecution. Thereafter, the writ petition was restored in the year 2017 by way of filing MCC No. 1556/2015. On 23. 07. 2018, 27. 08. 2018 and 01. 10. 2019 also the interim order was not continued. The interim order was thereafter continued only on 05. 11. 2019. 5. Thus, it appears that the interim order was not continued after 20. 01. 2015 till 05. 11.
2019. The construction is said to be made in the year 2018. Even otherwise, by a separate order passed today, the writ petition has been dismissed on merits. 6 . In view of the aforesaid, no contempt is made out. The contempt petition sans merits and stands dismissed. Signature Not Verified Signed by: RAJESH KUMAR Signing time: 1/29/2024 5:33:01 PM (VIVEK JAIN) JUDGE rj Signature Not Verified Signed by: RAJESH KUMAR Signing time: 1/29/2024 5:33:01 PM